NR 409.09(2)(b)1.
1. The unit shall be repowered with a qualifying repowering technology in order to comply with the emissions limitations for sulfur dioxide; or
NR 409.09(2)(b)2.
2. The unit shall be replaced by a new utility unit that has the same designated representative and that is located at a different site using a qualified repowering technology and the existing unit shall be permanently retired from service on or before the date on which the new utility unit commences commercial operation.
NR 409.09(2)(c)
(c) Submittal dates. In order to apply for a repowering extension, the designated representative of a unit under
par. (a) shall:
NR 409.09(2)(c)1.
1. Submit to the department, by January 1, 1996, a complete repowering extension plan;
NR 409.09(2)(c)2.
2. Submit to the administrator before June 1, 1997, a complete petition for approval of repowering technology in accordance with
40 CFR 72.44 (d) and submit a copy to the department; and
NR 409.09(2)(c)3.
3. If the repowering extension plan is submitted for conditional approval, submit to the department by December 31, 1997, a notification to activate the plan in accordance with
sub. (1) (c).
NR 409.09(2)(d)
(d) Contents of repowering extension plan. A complete repowering extension plan shall be sent to the department and include the following elements:
NR 409.09(2)(d)2.
2. The unit's federally-approved state implementation plan sulfur dioxide emissions limitation.
NR 409.09(2)(d)3.
3. The unit's 1995 actual SO
2 emissions rate or best estimate of the actual emissions rate; provided that the actual emissions rate is submitted to the department by January 30, 1996.
NR 409.09(2)(d)4.
4. A schedule for construction, installation and commencement of operation of the repowering technology approved or submitted for approval to the administrator under
40 CFR 72.44 (d) with dates for the following milestones:
NR 409.09(2)(d)4.b.
b. For a plan under
par. (b) 1., removal of the existing unit from operation to install the qualified repowering technology.
NR 409.09(2)(d)5.a.
a. Identification of the new unit. A new unit may not be included in more than one repowering extension plan.
NR 409.09(2)(d)5.c.
c. Certification that the new unit has the same designated representative as the existing unit.
NR 409.09(2)(d)5.d.
d. Certification that the existing unit shall be permanently retired from service on or before the date the new unit commences commercial operation.
NR 409.09(2)(e)1.1. The department may not approve a repowering extension plan until the administrator makes a conditional determination that the technology is a qualified repowering technology, unless the department approves the plan subject to the conditional determination of the administrator.
NR 409.09(2)(e)2.a.a. Upon a conditional determination by the administrator that the technology to be used in the repowering extension plan is a qualified repowering technology and a determination by the department that the plan meets the requirements, the department shall issue the acid rain portion of the operation permit, including the approved repowering extension plan and a schedule of compliance with enforceable milestones for construction, installation and commencement of operation of the repowering technology and other requirements necessary to ensure that emission reduction requirements under this section are met.
NR 409.09(2)(e)2.b.
b. Except as otherwise provided in
par. (f), the repowering extension shall be in effect starting January 1, 2000 and ending on the day before the date specified in the acid rain portion of an operation permit, on which the existing unit shall be removed from operation, to install the qualifying repowering technology, or shall be permanently removed from service for replacement by a new unit with the technology; provided that the repowering extension shall end no later than December 31, 2003.
NR 409.09(2)(e)2.c.
c. The portion of the operation permit specifying the repowering extension and other requirements under
subd. 2. a. shall be subject to the administrator's final determination, under
40 CFR 72.44 (d) (4), that the technology to be used in the repowering extension plan is a qualifying repowering technology.
NR 409.09(2)(f)1.1. If, at any time before the end of the repowering extension under
par. (e) 2. b., the designated representative of a unit governed by an approved repowering extension plan submits the notification under
s. NR 409.13 (2) (d) that the owners and operators have decided to terminate efforts to properly design, construct and test the repowering technology specified in the plan before completion of construction or startup testing, the designated representative may submit to the department a requested significant permit revision demonstrating that the efforts were in good faith. A copy of the requested significant permit revision shall be submitted to the administrator. If the demonstration is to the satisfaction of the administrator, the unit may not be deemed in violation of the act because of a termination and the department shall revise the operation permit in accordance with
subd. 2.
NR 409.09(2)(f)2.
2. Regardless of whether notification under
subd. 1. is given, the repowering extension shall end beginning on the earlier of the date of the notification or the date by which the designated representative was required to give the notification under
s. NR 409.13 (2) (d).
NR 409.09(2)(f)3.
3. The designated representative of a unit governed by an approved repowering extension plan may submit to the department a proposed significant permit revision demonstrating that the repowering technology specified in the plan was properly constructed and tested on the unit but was unable to achieve the emissions reduction requirements specified in the plan and that it is economically or technologically infeasible to modify the technology to achieve the emission limits. A copy of the requested significant permit revision shall be submitted to the administrator. In order to be properly constructed and tested, the repowering technology shall be constructed at least to the extent necessary for direct testing of multiple combustion emissions, including sulfur dioxide and nitrogen oxides, from the unit while operating the technology at nameplate capacity. If the demonstration is to the satisfaction of the administrator:
NR 409.09(2)(f)3.a.
a. The unit may not be deemed in violation of the act because of the failure to achieve the emissions reduction limitations;
NR 409.09(2)(f)3.b.
b. The department shall revise the acid rain portion of the operation permit in accordance with
subd. 3. c. and
d.;
NR 409.09(2)(f)3.c.
c. The existing unit may be retrofitted or repowered with another clean coal or other available control technology; and
NR 409.09(2)(f)3.d.
d. The repowering extension shall continue in effect until the earlier of the date the existing unit commences commercial operation with the control technology or December 31, 2003.
NR 409.09(2)(g)1.a.a. Sulfur dioxide allowances allocated during the repowering extension under
pars. (e) 3. and
(f) to a unit governed by an approved repowering extension plan may not be transferred to any allowance tracking system account other than the unit accounts of other units at the same source as that unit.
NR 409.09(2)(g)1.b.
b. Any existing unit governed by an approved repowering extension plan shall be subject to the acid rain emissions limitations for nitrogen oxides in accordance with section 407 of the act (
42 USC 7651f) and
s. NR 409.065 beginning on the date that the unit is removed from operation to install the repowering technology or is permanently removed from service.
NR 409.09(2)(g)1.c.
c. No existing unit governed by an approved repowering extension plan shall be eligible for a waiver under section 111 (j) of the act (
42 USC 7411 (j)).
NR 409.09(2)(g)1.d.
d. No new unit governed by an approved repowering extension plan shall receive an exemption from the requirements imposed under section 111 of the act (
42 USC 7411).
NR 409.09(2)(g)2.
2. Each unit governed by an approved repowering extension plan shall comply with the special reporting requirements of
s. NR 409.13 (2).
NR 409.09(2)(g)3.a.a. The owners and operators of a unit governed by an approved repowering plan shall be liable for any violation of the plan or this section at that or any other unit governed by the plan.
NR 409.09(2)(g)3.b.
b. The units governed by the plan under
par. (b) 2. shall continue to have a common designated representative until the existing unit is permanently retired under the plan.
NR 409.09(2)(g)4.
4. Except as provided in
par. (f), a repowering extension plan may not be terminated after December 31, 1999.
NR 409.09 History
History: Cr.
Register, April, 1995, No. 472, eff. 5-1-95; renum. (1) (a) to be (1) (a) 1., cr. (1) (a) 2. and am. (1) (b) (intro.), (c) (intro.), 1., (d) 1., (2) (f) 1., 3. (intro.) and (g) 1. b.,
Register, November, 1999, No. 527, eff. 12-1-99.
NR 409.10
NR 409.10 Acid rain portion of an operation permit. NR 409.10(1)(a)(a) Each acid rain portion of an operation permit, including any draft or proposed acid rain portion of an operation permit, shall contain the following elements:
NR 409.10(1)(a)1.
1. All elements required for a complete acid rain portion of an operation permit application under
s. NR 409.08 (2), as approved or adjusted by the department.
NR 409.10(1)(a)2.
2. The applicable acid rain emissions limitation for sulfur dioxide.
NR 409.10(1)(a)3.
3. The applicable acid rain emissions limitation for nitrogen oxides.
NR 409.10(2)
(2) Permit shield. Each affected unit operated in accordance with the acid rain portion of an operation permit that governs the unit and that was issued in compliance with title IV of the act (
42 USC 7651 to
7651o), as provided in this chapter,
40 CFR parts 72,
73,
74,
75,
76,
77 and
78 and the regulations implementing section 407 of the act (
42 USC 7651f), shall be deemed to be operating in compliance with the acid rain program, except as provided in
s. NR 409.06 (7) (f).
NR 409.10 History
History: Cr.
Register, April, 1995, No. 472, eff. 5-1-95; am. (2),
Register, November, 1999, No. 527, eff. 12-1-99.
NR 409.11
NR 409.11 Acid rain portion of an operation permit issuance procedures. NR 409.11(1)
(1)
General. The department shall issue or deny all acid rain portions of title V permits in accordance with s.
285.62, Stats. and
s. NR 409.10.
NR 409.11 Note
Note: These rules are intended to follow the requirements in
40 CFR 72.72 regarding state permit program approval criteria.
NR 409.11(1)(a)1.1. On or before December 31, 1997, the department shall issue an operation permit with a phase II acid rain portion to each affected source whose designated representative submitted a timely and complete application for the acid rain portion of its operation permit by January 1, 1996 in accordance with
s. NR 409.07 (1) and which meets the requirements of this chapter and
ch. NR 407.
NR 409.11(1)(a)2.
2. Not later than January 1, 1999, for each unit subject to an acid rain NO
x emissions limitation, the department shall begin the process of amending the acid rain portion of an operation permit under
s. NR 409.12 (4) to add any NO
x early election plan that was approved by the administrator under
40 CFR 76.8 and has not been terminated and begin the process of amending the acid rain portion of the permit to add the acid rain program nitrogen oxides requirements; provided that the designated representative of the affected source submitted a timely and complete acid rain portion of an operation permit application for nitrogen oxides in accordance with
s. NR 409.07 (1). The amending may not affect the term of the acid rain portion of an operation permit.
NR 409.11(1)(a)3.
3. Each acid rain portion of an operation permit issued in accordance with this chapter shall have a term of 5 years commencing on its effective date, provided that, at the discretion of the department, the first acid rain portion of an operation permit for Phase II may have a term of less than 5 years where necessary to coordinate the term of the permit with the term of an operation permit issued by the department to the source. Each acid rain portion of an operation permit issued in accordance with
subd. 1. shall take effect by the later of January 1, 2000 or, where the permit governs a unit under
s. NR 409.01 (1) (a) 3., the deadline for monitor certification under
40 CFR part 75.
NR 409.11(1)(a)4.
4. The acid rain portion of an operation permit shall be binding on any new owner or operator or designated representative of any source or unit governed by the permit.
NR 409.11(1)(b)
(b) Acid rain portion of an operation permit requirements. Each acid rain portion of an operation permit shall contain all applicable acid rain requirements, shall be a portion of the operation permit that is complete and segregable from all other air quality requirements and may not incorporate information contained in any other documents, other than documents that are readily available.
NR 409.11(2)(a)(a) Appeals of the acid rain portion of an operation permit issued by the department that do not challenge or involve decisions or actions of the administrator under
40 CFR parts 72,
73,
74,
75,
76,
77 and
78 shall be conducted according to the procedures in
ch. NR 407 and ss.
285.13 (1),
285.81 and
227.40 to
227.60, Stats. The permit shield under
s. NR 409.10 (2) shall continue to be in effect during the appeal process. Appeals of the acid rain portion of a permit that challenge or involve decisions or actions of the administrator shall follow the procedures under
40 CFR part 78 and section 307 of the act (
42 USC 7607). Decisions or actions include, but are not limited to, allowance allocations, determinations concerning alternative monitoring systems and determinations of whether a technology is a qualifying repowering technology.
NR 409.11(2)(b)
(b) No state administrative or judicial appeal of the acid rain portion of an operation permit may be allowed to commence more than 30 days following issuance of the acid rain portion of an operation permit, as provided by ss.
285.81 and
227.53, Stats.
NR 409.11(2)(c)
(c) The administrator may intervene as a matter of right in any state administrative appeal of an acid rain portion of an operation permit or denial of an acid rain portion of an operation permit.
NR 409.11(2)(e)
(e) The department shall serve written notice on the administrator of any state administrative or judicial appeal concerning an acid rain provision of any operation permit or denial of an acid rain portion of any operation permit within 30 days of the filing of the appeal.
NR 409.11(2)(f)
(f) The department shall serve written notice on the administrator of any determination or order in a state administrative or judicial proceeding that interprets, modifies, voids or otherwise relates to any portion of an acid rain portion of an operation permit.
NR 409.11 History
History: Cr.
Register, April, 1995, No. 472, eff. 5-1-95; am. (2) (a),
Register, December, 1996, No. 492, eff. 1-1-97; am. (1) (a) 1., 3., (2) (a) and (f), r. (1) (c) and (2) (d),
Register, November, 1999, No. 527, eff. 12-1-99.
NR 409.12
NR 409.12 Revisions of acid rain provisions. NR 409.12(1)(a)(a) This section governs revisions to the acid rain portion of any operation permit issued by the department under
ch. NR 407. Any determination or interpretation by the department or by the state, including a state court, modifying or voiding any provision of the acid rain portion of an operation permit shall be subject to review by the administrator in accordance with
40 CFR 70.8 (c) as applied to permit modifications, unless the determination or interpretation is an administrative revision approved in accordance with
40 CFR 72.83 and
sub. (4).
NR 409.12(1)(b)
(b) A request for a permit revision may be submitted to the department at any time. No permit revision may affect the duration of the permit to be revised. No permit revision may excuse any violation of an applicable requirement of the acid rain program that occurred prior to the effective date of the revision.
NR 409.12(1)(c)
(c) The terms of the acid rain portion of the operation permit shall apply while the request for a permit revision is pending, except as provided in
sub. (4) for administrative permit revisions.
NR 409.12(1)(e)
(e) Any request for a permit revision to incorporate a compliance option that was not submitted for approval and comment during the permit issuance process, or involving a change in a compliance option that was previously submitted, shall meet the requirements for applying for that compliance option under subpart D of
40 CFR part 72 and
40 CFR parts 74 and
76.
NR 409.12(1)(f)
(f) For permit revisions not described in
sub. (2) or
(3), the department may, at its discretion, determine whether the revision request will be processed under
sub. (2) or
(3).
NR 409.12(1)(g)
(g) Any designated representative who fails to submit any relevant information or who has submitted incorrect information in a permit revision shall, upon becoming aware of the failure or incorrect submittal, promptly submit the supplementary information or corrected information to the department.
NR 409.12(2)(a)(a) Applications for the following revisions shall be processed as significant permit revisions except as provided in
sub. (4) (a) 11.:
NR 409.12(2)(a)1.
1. Relaxation of an excess emission offset requirement after approval of the offset plan by the administrator.
NR 409.12(2)(a)2.
2. Incorporation of a final nitrogen oxides alternative emission limitation pursuant to section 407 (d) of the act (
42 USC 7651f(d)).